Getting Your Palisades Rebuild Reconnected to the Sewer: S Permit, Lateral Video and Septic Reuse
If your Palisades home was on the City sewer, the City requires reconnection before it issues a certificate of occupancy. That starts with an S Permit, a video (CCTV) inspection of the existing lateral and a City inspection. A lateral in good condition can usually be reused; one that could damage the street must be repaired first.

Most of Pacific Palisades is on the City of Los Angeles sewer, so for most rebuilds the question is not septic but the sewer lateral: the private pipe from your house to the main in the street. The fire most likely did not reach it, but years of roots, settlement and heavy rebuild traffic may have. The City wants to know its condition before your home is reconnected.
If you were on the sewer: reconnection is required
The City's rebuild guidance says a property that was on the public sewer must reconnect as part of the rebuild, and the certificate of occupancy will not issue until it does. The steps, in order:
- Apply for an S Permit (sewer connection) on the Bureau of Engineering permits portal. Select "Windstorm and Fires January 2025", choose the reconnection work type and note that you are requesting reconnection and CCTV.
- Schedule the pre-construction inspection with the Bureau of Contract Administration before any reconnection work.
- Video the existing lateral (CCTV) at that inspection. The City inspector witnesses and documents the condition.
What happens after the video
- A 4-inch lateral in good condition can generally be reconnected. Upsizing to 6 inches is not required just to reconnect.
- A lateral in poor condition that is not a threat to the street may be reconnected as-is, and the owner may be asked to sign an acknowledgment of the condition and of responsibility for future repairs.
- A lateral that could damage the street, cause a sinkhole or leak has to be repaired or replaced first.
- One lot, one lateral: shared laterals are generally not allowed for new reconnections.
- The owner maintains the lateral, including the part under the street.
If you were on septic
Some hillside lots in the City were on septic. For one- and two-family homes damaged in the 2025 fires, the City allows two options: reuse the existing system, or abandon it and connect to the sewer where a sewer is available. Reuse requires a permitted system, no increase in bedrooms or design flow over the prior permitted home, and an evaluation report from a qualified contractor or qualified professional reviewed by LADBS Grading. Properties outside the City, such as Topanga and the canyons in unincorporated LA County, go through LA County Public Health instead, and Malibu runs its own program.
Fees and fee relief
The City waived many permit and clearance fees for owners at the time of the fire, for rebuilds up to 110 percent of the original area. The waiver must be repaid if the property is sold before the certificate of occupancy. The fee-waiver guide does not list sewer connection charges, so confirm those with the City for your project.
For the work itself, see Sewer Lateral Repair and Installation and Septic to Sewer Conversion.
Why this belongs early in the rebuild
A lateral that has to be replaced means work in the street, a separate permit and an inspection, and a hillside lot can add shoring and traffic control. Finding that out after the house is framed costs time. Video the lateral as soon as the lot is accessible.
Where we fit
Underground work done safely and signed off, by a bonded and licensed Cal/OSHA T-1 excavation contractor. JF Prieto Engineering Construction, Inc. holds CA Lic. #525452 · Class A + B + Haz, including the California Class A General Engineering license, and is on the City of Los Angeles approved list of Bonded Sewer Contractors, so we can pull the S Permit for a new lateral and do the work in the street ourselves. We locate and video the lateral, document what we find, prepare the scope in writing, and replace or repair the lateral, septic tank or connection with our own crew. Where a design or a stamped report is required, a licensed engineer or geologist prepares it and we build to it. Your expediter files the permits with the City, or we file them when needed. Call (800) 606-3880 or request a site visit.
Sources
- City of LA Recovery, S Permit Handout (2026): recovery.lacity.gov
- City of LA Recovery, Septic and Sewer Connection Options and Pathways (2026): recovery.lacity.gov
- City of LA Recovery, Rebuilding: recovery.lacity.gov/rebuilding
- LADBS Information Bulletin P/BC 2026-160, Reuse of Existing Septic Systems for Wildfire Projects (effective 2 Mar 2026): dbs.lacity.gov
- LADBS, Palisades Fire Permit Fee Waivers and Refund Guide: dbs.lacity.gov/palisades-fire-permit-fee-waivers-refund-guide