What a Civil Subcontractor Builds at a Landfill Gas Flare Station

Giulliano J. Prieto

Senior Construction Project Engineer · VP Project Management

At a landfill gas flare station, the civil subcontractor builds everything around the environmental firm's process equipment: the flare, blower and control building foundations, the subgrade preparation, the gas header and electrical trenching, the storm drain and swales, and the paving. The engineer of record designs it; the civil sub builds it to the approved plans.

What a Civil Subcontractor Builds at a Landfill Gas Flare Station

An environmental firm brings the process to a landfill gas flare station: the gas collection system, the flare, the blowers and the controls. Everything around that process is civil work. The pads and foundations, the trenches for the gas header and the power, the drainage and the road back in all have to be built, inspected and handed over before the equipment can be set.

What does the civil scope of a flare station include?

On the flare stations we have built as a civil subcontractor, the civil package has covered these parts.

  • Flare and equipment foundations. Flare, blower skid, VFD and control building foundations and pads, including pile-supported pads where the plans call for them.
  • Subgrade preparation. Over-excavation, recompaction and pad grading to the geotechnical engineer's requirements, tested by the project's inspector.
  • Gas header and condensate trenching. Excavation, bedding, backfill and surface restoration for header, lateral and condensate lines, built around the environmental firm's piping crew.
  • Electrical underground. Duct banks, conduit, pull boxes, vaults and equipment pads for the power and controls.
  • Storm drain and erosion control. Storm drain replacement, concrete swales, splash walls and downdrains.
  • Paving and access. Asphalt paving, trench patching and access-road repair once the underground is done.

In what order does the work go?

The sequence matters more on a landfill than on most sites, because the gas system has to keep running while the station is built around it.

  1. Locate and pothole. Existing headers, power and water lines are located and the crossings exposed by hydrovac potholing before any trench is cut.
  2. Prepare the subgrade. The pad areas are over-excavated and recompacted to the geotechnical engineer's requirements.
  3. Build the foundations and underground. Forming, rebar and concrete for the pads, plus the trenches, duct banks, vaults and storm drain, all to the engineer's plans.
  4. Inspect before cover. Nothing is backfilled or poured until the inspector or the engineer signs off.
  5. Restore and hand off. Backfill, paving, swales and fencing go back, and the pads are turned over for the equipment to be set.

What makes landfill work different?

A landfill is an operating site. Trucks keep moving, landfill gas can be present, and the gas system stays live. Crews work to the site's health and safety plan, including landfill gas awareness, hot-work controls and the site's traffic rules. Every excavation is run by a competent person under a Cal/OSHA trench and excavation permit.

Standby is part of the job too. The civil crew often waits while the piping crew sets a header or the electrician pulls wire, so the schedule and the bid both need to account for it.

Who designs the foundations?

The engineer of record. Design of the gas collection system, the flare and its foundations stays with the engineer of record, and the geotechnical engineer sets the subgrade requirements. The civil contractor builds to the approved plans, and any field change goes back to the engineer before it is built.

Where we fit

JF Prieto Engineering Construction, Inc. has worked as the civil subcontractor at active landfills in Castaic, Palmdale, Santa Paula, Corona, Sylmar and Santa Maria since 2022, with our own crews, excavators, rollers, shoring and hydrovac truck. See our environmental and landfill civil service and the landfill work on our projects page, or send plans and a bid schedule to projects@prietoengineering.com.

CA Lic. #525452 · Class A + B + Haz

Share this article

Email Facebook LinkedIn X WhatsApp Text

Sources

JF Prieto Engineering Construction, Inc. field practice on landfill flare station projects, 2022 to 2026.