Send the civil, structural and electrical plans, the geotechnical report, your bid schedule, the site's health and safety plan, the subcontract requirements and any as-builts of existing headers and utilities. With those, a civil subcontractor can price your scope line by line instead of carrying allowances.

Bidding the Civil Package on a Landfill Project: What to Send Your Civil Sub

A civil subcontractor can only price what it can see. On a landfill or environmental project, a complete bid package lets the civil sub price your scope line by line, with fewer allowances and fewer surprises after award. Here is what we ask for, and why each item changes the number.

What should the bid package include?

  • The plans. Civil, structural and electrical sheets. Foundation size, depth and rebar drive the concrete price; trench lengths and depths drive the underground.
  • The geotechnical report. It sets the over-excavation and recompaction, and whether piles are needed under the pads.
  • Your bid schedule. We price line by line to match it, so you can compare bids and award without guessing what is included.
  • The site's health and safety plan. Working hours, gas awareness and hot-work requirements affect crew time.
  • The subcontract requirements. Insurance, bonding, prevailing wage and certified payroll, and any prequalification system the site uses.
  • Existing utility information. As-builts of headers, power and water lines, so potholing and crossings can be priced.

What drives the civil price?

  • Foundation size, depth and rebar, and whether piles or over-excavation are required
  • Distance and depth of trenching, and how many existing headers and utilities have to be crossed
  • Site access, haul routes, and where export can go on site
  • Standby time while equipment, piping or other trades are set
  • The site's safety requirements and working hours
  • Prevailing wage and certified payroll on public projects

Testing, inspection and agency fees are usually paid by the owner directly and are not in the civil price.

Why walk the site before pricing?

Drawings rarely show everything on a working landfill. A walk shows the access, the work area, the existing gas headers and utilities, and where trucks and equipment can stage. A walk often settles a question that would otherwise become an allowance.

Do civil subs take prevailing-wage work?

Many do. On landfill and environmental projects, we take prevailing-wage work as a subcontractor to the environmental firm or the prime contractor, including public solid waste projects. We do not bid public works as the prime contractor. Tell us the wage determination and the certified payroll requirements up front, so the price reflects them.

Where we fit

JF Prieto Engineering Construction, Inc. is a Class A civil subcontractor for the foundations, underground, drainage and paving around environmental systems. See our environmental and landfill civil service, then send the plans, the geotechnical report, the bid schedule and the subcontract requirements to projects@prietoengineering.com, and we will price our scope to match.

CA Lic. #525452 · Class A + B + Haz

Share this article

Email Facebook LinkedIn X WhatsApp Text

Sources

JF Prieto Engineering Construction, Inc. bidding practice on landfill and environmental projects, 2022 to 2026.